DEVELOPMENT OF A SOLAR ENERGY
PROJECT AT MUNICIPALLY OWNED
WELLFIELD IN ACTON, MASSACHUSETTS
The purpose of this Request for Proposals (“RFP”) is to seek proposals from qualified and experienced renewable energy Developers interested in implementing one or two renewable energy system(s) which will guarantee electricity generation to supply renewable electricity to the Water Supply District of Acton. The Developer will lease Water Supply District of Acton land, to develop, own and operate one or two solar energy projects and enter into a long term Power Purchase Agreement (PPA) selling the energy output to the District (sometimes herein referred to as the Acton Water District). If more electricity is generated than is needed by the District, then this “surplus” energy may be sold to other non-District off-takers, with other Acton Municipal facilities receiving the right of first refusal.
The Acton Water District (AWD) intends to lease District owned property for the installation of solar collectors, inverters and cabling for a solar array at their municipal wellfield sites on 16 Knox Trail and/or 62 Lawsbrook Road. The lease term will be for a term of 20 years. The lease term may be extended for two consecutive five year terms, but will require a vote of the Board of Water Commissioners.
The AWD will enter into a long term Power Purchase Agreement (PPA) with the successful Developer. The agreement between the AWD and the selected solar developer will take the form of a standard contract involving the generation and purchase of the electricity generated by the installed solar system at a specified price, for a specific period of time. The bidder will offer the AWD buy back options with ownership transfer of the system at the end of the PPA, or earlier.
The Selected Developer will be responsible for the interconnection study, permitting, and subsequent interconnection costs. The Selected Developer will construct, own and operate the solar energy project. The Selected Developer will retain all Solar Renewable Energy Certificates (SREC), Environmental Credits, Tax Credits, and other credits or grants derived from the solar energy project. The Acton Water District proposes to purchase the solar energy from the project under a net metering agreement.
CONTACT PERSON
All communication regarding this RFP must be made in writing and directed to:
Chris Allen, District Manager
Acton Water District
PO Box 953, Acton, MA 01720
(978) 263-9107
Email:
Once your proposal is ready to be sent, Send us the proposal using dropbox by clicking here.
Use this link to submit the sealed bid price Send us the sealed bid using dropbox by clicking here.
Description of Hyperlink |
|
Hyperlinked document for Download |
|
Submitted Questions (posted 10/25/17 (pdf) |
|
F.A.Q | |
Financials Table (posted 10/25/2017) |
|
Excel version or PDF Version | |
Site Plan Addendum (posted 10/20/2017) (pdf) |
|
Site Plan Addendum | |
The full request for proposal (pdf) |
|
Download the RFP document | |
ATTACHMENT A1- Site Images (pdf) |
AWD Knox Trail Contiguous Properties | ||
ATTACHMENT A1- Site Images (pdf) |
AWD Knox Trail Satellite Image | ||
ATTACHMENT A1- Site Images (pdf) |
|
||
ATTACHMENT A1- Site Images (pdf) |
|
||
ATTACHMENT A2- Sites with Illustrative Solar Layouts (pdf) |
|||
ATTACHMENT A2- Sites with Illustrative Solar Layouts (pdf) | |||
ATTACHMENT A3 (pdf) |
|
||
ATTACHMENT A4 (pdf) | |||
ATTACHMENT A5 (pdf) |
Bureau of Resource Protection Solar in Zone 1 Policy & Guide |
||
ATTACHMENT A6 (excel file) | |||
ATTACHMENT A6-1 (pdf) (posted 11/1/2017) | |||
ATTACHMENT A7 (pdf) | |||
ATTACHMENT A7 (pdf) | |||
ATTACHMENT A8 (excel file) | |||
Exhibit 1 - Draft Lease and PPA Agreements (pdf) | |||
Request for Proposal Legal Advertisement published (pdf) |